Lagos announces preferred bidder for $2.5bn Fourth Mainland Bridge

Fourth Mainland

Bidder emerges for Third Mainland Bridge

The Lagos State Government on Friday announced Messrs. CCECC-CRCCIG Consortium as the preferred bidder for the proposed Fourth Mainland Bridge.

Speaking at a news conference at the Bagauda Kaltho Press Centre, Alausa, Ikeja, Lagos, the Special Adviser to the Governor on Public-Private Partnerships (PPP), Ope George said CCECC-CRCCIG Consortium won the preferred bidder and would undertake the proposed construction of the Fourth Mainland Bridge.

He said Messrs. Mota-Engil (Nigeria and Africa) and CCCC & CRBC Consortium are the reserved bidder for the proposed Fourth Mainland Bridge.

The joint press conference was addressed by the Commissioner for Information and Strategy, Gbenga Omotoso; Special Adviser to the Governor on Works and Infrastructure, Engr. Aramide Adeyoye and George.

George said the Fourth Mainland Bridge Project, which is a proposed Public Private Partnership (PPP) transport infrastructure development, would comprise the construction and operation of a greenfield tolled road and bridge with a design speed of 120km/h, including the development of adjacent real estates.

He added that the bridge, when completed, would become the second longest in Africa with three toll plazas, nine interchanges, a 4.5km Lagoon Bridge and an eco-friendly environment. I

He said the bridge was also expected to span about 37kilometres, starting from Abraham Adesanya in Ajah, on the Eti-Osa-Lekki-Epe corridor and traverse the North West towards the Lagoon shoreline of the Lagos-Ibadan Expressway via Owutu/Isawo in Ikorodu.

In his words, “You will recall that the Lagos State Government commenced a Competitive Bidding process for the selection of a Concessionaire, by the issuance of the Request for Expressions of Interest (REOI) on 27th of November, 2019. A total of 52 responses were received with 32 being responsive”.

Related News

“Subsequently, a Request for Quotation (RFQ) was issued on 10th February 2020 to the 32 eligible applicants and responses were received on 15th April, 2020 with a total of 15 responses. Upon evaluation, six bidders met the criteria to progress to the Request for Proposal (RfP) stage.”

The Special Adviser restated that the bridge would reduce congestion on the existing Carter, Eko and Third Mainland Bridges while opening new areas of the City for future developments.

George disclosed that the proposed 37km bridge is worth between $2.5 billion and $3 billion.

Also speaking, Adeyoye said the proposed Fourth Mainland Bridge is expected to be completed in 54 months, adding that 16 alignments were being considered.

She disclosed that structures to be affected and demolished to pave way for the project had been pruned from 2,000 to 800.

Speaking, Commissioner for Information and Strategy, Omotoso said those whose structures would be demolished would be duly compensated and that affected property owners should have no fear.

 

 